Header starkregenkonzept image w2000 h670

Trench Shoring - Linear Shoring

LINEAR SHORING PROVIDES WORKING SPACE IN XXL

TRENCHLESS CROSSING

Until now, the Asbach district of the Thuringian town of Schmalkalden had not been connected to the municipal sewer system. This was made up for in two steps: the first 200 meters of the planned combined sewer were already laid in 2014, and a further 500 meters were installed in 2015 in a connection order. At the same time, the wastewater association "Schmalkalden and surroundings" would like to create additional volume to accommodate rainwater.

A decision was made in favor of a two-component solution: A 51-meter-long storage sewer designed with DN 3000 GRP pipes is to ensure the controlled release of rainwater to the sewer system during future heavy rainfall events, while an additional rainwater overflow structure made of precast concrete elements is to relieve the Schmalkalden sewage treatment plant.

With linear shoring of the E+S product brand, the contractor Herzog-Bau GmbH, Tüttleben, relied on a shoring system from terra infrastructure for securing the excavation pits. This paid off in many respects: The technical possibilities of the linear shoring system, in particular the use of the U-type roller unit, ensured the necessary pipe clearance height during the construction of the reservoir channel. And with the installation of a longitudinal outer waling and bottom bracing of the middle girder pairs, the preconditions for the installation of the large-format precast concrete elements of the stormwater overflow basin were created on the construction site.

The installation of the stormwater overflow, which was constructed from precast concrete components, required a particularly large installation window.

Belting provides large construction window

For the stormwater overflow basin, a structure consisting of precast elements weighing up to 37 tons each was used. The imposing size of the structure was also reflected in the dimensions of the excavation pit, which had a depth of between 4 and 5 meters and a clear width of 3.65 meters. To secure it, a special technical solution was required that extended the possibilities of conventional linear shoring.

First, two modules of linear shoring were installed in the excavation. Longitudinally attached outer walers and ground bracing of the middle pair of beams created the conditions for the installation of the large-format concrete components. Shortly before installation, the middle roller unit could then be completely pulled out of the shoring. The externally attached girder structure now took the entire load.

Data & Facts

Builder
Wastewater association "Schmalkalden and surroundings
Delivery
Stepped linear shoring consisting of linear shoring soldiers, inner and outer shoring panels, U-type roller unit

you might also be interested in

  • Flood Protection along the railway line in Minnesota

    A railway line that crosses the Chippewa River, Minnesota is regularly affected by flooding and should be provided with flood protection.


    To the post
  • Rain Overflow Basin in Chemnitz

    Renovation of sewer, electricity, gas, drinking water, lighting and communication and construction of a storm water overflow structure in the area of the traffic junction.


    To the post
  • Flood Protection System in Dresdens Old Town

    The city of Dresden lies on several rivers that have overflowed their banks at regular intervals in recent years. The city and state have therefore been investing in flood protection for years.


    To the post